Primavera P6 DCMA 14-point schedule quality checks in your own words
Ask Primavera P6 schedule quality questions in Claude, ChatGPT or Copilot: missing logic, hard constraints, high float, lags and invalid dates by project.
Short answer
Primavera P6 schedule quality checks with Nexatron mean asking DCMA 14-point questions in your own words, from the Nexatron app or from Claude, ChatGPT and Copilot: open ends, hard constraints, leads and lags, high float and invalid dates per update. Oracle Primavera is available, with user-level access: Nexatron inherits existing Primavera permissions.
Example questions
- What share of incomplete activities in each project have no predecessor or no successor?
- How many relationships use a negative lag, and which activities do they connect?
- Which activities carry hard constraints such as mandatory start or mandatory finish, and why?
- How many incomplete activities have total float above 44 working days in this update?
- Which activities show an actual date after the data date or a forecast date before it?
- How did the count of failed checks change between the last two monthly submissions?
Who asks
- Owner’s scheduler
- Reviews every contractor submission against the contract’s schedule specification. Asks for the DCMA checks per project, the activities failing each, and whether the count improved since the last submission.
- Contractor planner
- Runs the same checks before submitting, so the update is not rejected. Wants the failing activities listed by WBS with the reason, ready to fix.
- PMO schedule standards lead
- Tracks schedule health across the portfolio. Needs a pass or fail per check per project with the thresholds the organization agreed.
What the answer reads in Oracle Primavera
- Activities
- Activity type, status, original and remaining duration, total float, constraint type and actual and forecast dates. Activity type decides which activities enter the check population.
- Relationships
- Type and lag for every link, used for missing logic, leads, lags and the share of finish-to-start relationships.
- Calendars
- Work periods per calendar, which convert lag and float thresholds such as 44 working days into the right span.
- Project data date
- The date that invalid-date checks compare actual and forecast dates against.
Often asked beside: Oracle Aconex.
Agree these definitions first
- Population
- Which activities a check counts: usually incomplete task-dependent activities, leaving out milestones, level of effort and WBS summaries.
- Thresholds
- The tolerance for each check, such as 5 percent for missing logic or 44 working days for high float, as agreed with the owner.
- Hard constraint
- Which constraint types count as hard, such as mandatory start, mandatory finish, start on and finish on.
- Data date
- The update being checked, since invalid-date checks compare actual and forecast dates with that date.
What a good answer contains
- Each check with its numerator, denominator, threshold and result, so a reader can recompute it.
- The check population stated: usually incomplete tasks, with milestones, level-of-effort and summary activities handled as agreed.
- The failing activities for each check, with WBS and activity name, not only a percentage.
- A comparison with the previous submission on the same thresholds, showing which failures are new.
- Notes where a failure is often justified, such as a contractual milestone constraint, so it is reviewed rather than auto-rejected.
Where the data misleads
- Different populations
- One tool counts milestones and level-of-effort activities in missing logic, another excludes them. The same schedule can pass in one and fail in the other.
- Thresholds read as rules
- The DCMA thresholds are guidance. A long procurement activity or a contractual constraint can fail a check legitimately, so the answer marks rather than condemns.
- Lag in the wrong calendar
- Lags are measured on the predecessor’s, successor’s or a 24-hour calendar depending on a project setting. A lag check that ignores it misjudges long lags.
- Checking the wrong copy
- Running the checks on the baseline or on an unpublished working copy instead of the submitted update gives results nobody else can reproduce.
A worked example
Question What share of incomplete activities in each project have no predecessor or no successor?
- Scope comes first: the projects the user can open in Primavera, at their current data dates.
- It builds the population of incomplete task-dependent activities, leaving out the start and finish milestones by the agreed rule.
- It counts activities lacking a predecessor or a successor and divides by the population, against the agreed 5 percent threshold.
- The answer lists the failing activities by WBS for each project, compares with the last update, and shows the definition and query used.
How it works
1. Connect Oracle Primavera
An administrator enables Oracle Primavera in your Nexatron workspace. Nexatron reads activities, relationships, constraints and calendars through the Primavera Cloud REST API or the P6 EPPM REST API.
2. User-level access
Users sign in with their own Primavera account (or your SSO), and Nexatron inherits their existing Primavera permissions. Their project security profiles decide which schedules can be checked, so a planner sees results for the projects they work on.
3. Agree the definitions
The planning lead approves the population and thresholds above once, so a check run by the owner’s scheduler matches the contractor’s.
4. What each answer shows
Questions only read Primavera. When a word such as “missing logic” or “high float” has more than one meaning, the answer says which reading it used and offers the others in one click. It reads Verified only once a named person on your team has reviewed the logic, with who and when shown. A question Nexatron cannot answer under your rules is declined, with the reason and what to do next.
5. Ask where your team works
People ask in the Nexatron app or through Nexatron’s hosted MCP server in Claude, ChatGPT and Microsoft Copilot. Each answer shows the definition, source and query it used.
Questions and answers
- Is the DCMA 14-point assessment required for every project?
- No. It started as a US defense guideline and many owners and contractors adopt it as a common baseline for schedule quality. Your contract’s schedule specification decides which checks and thresholds apply.
- Can we add our own checks beyond the fourteen?
- Yes. Checks such as activities without a resource, durations over a set length or missing activity codes are written once as definitions and run beside the standard ones.